September 2001
|
SAPP Grant allocated
|
|
June 2002
|
Initial meeting held with Follansbee requesting rate of
treatment and upgrade costs
|
|
September 2002
|
Letter to Follansbee providing flow information
|
|
December 2002
|
Preliminary plans provided to Follansbee and Ghosh
|
|
January 2003
|
Letter to Follansbee requesting rate of treatment
|
|
March 2003
|
Letter to Follansbee requesting rate of treatment
|
|
April 2003
|
Meeting held between BCPSD and Follansbee to discuss treatment
rate
|
|
May 2003
|
Letter to Follansbee requesting rate of treatment
|
|
July 2003
|
Letter from Follansbee providing treatment rate of $3.74
|
|
July 2003
|
Letter to Follansbee requesting method used to calculate
treatment rate
|
|
August 2003
|
Letter to Follansbee requesting data used in rate
calculation
|
|
August 2003
|
Received Rate Data
from Follansbee
|
|
November 2003
|
Special meeting held to discuss project progress
|
|
November 2003
|
Email to Follansbee recalculating treatment rate
|
|
December 2003
|
Letter to Follansbee requesting comments on revised rate
|
|
January 2004
|
Letter to BCPSD from Burgess and Niple
stating preliminary design is nearly complete, waiting on treatment rate to
finalize
|
|
January 2004
|
Meeting held to discuss treatment rate with Follansbee and
BCPSD
|
|
February 2004
|
Email to Follansbee requesting capacity and annual fees
associated
|
|
February 2004
|
Meeting held between BCPSD and Follansbee to discuss
treatment rate
|
|
February 2004
|
Email to BCPSD stating results of previous meeting
|
|
February 2004
|
Email to Follansbee Engineer providing flow data
|
|
February 2004
|
Letter from Follansbee providing treatment rate of $3.06
|
|
February 2004
|
Preliminary engineering report submitted to WVIJDC
|
|
February 2004
|
Thrasher Engineering procured for design and construction
services
|
|
February 2005
|
Amendment to Infrastructure Council to separate project
into multiple phases
|
|
February 2005
|
Notified by Follansbee treatment upgrade cost has
increased from $350,000 to $550,000
|
|
July 2005
|
Funding committed for Phase I of project
|
|
September 2005
|
Conference call with all parties to discuss Aid to
Construction amount and necessity for grit chamber
|
|
September 2005
|
Meeting at Follansbee WWTP to discuss upgrades
|
|
November 2005
|
Plans and specification submitted to WVDEP for review
|
|
December 2005
|
Estimate from Follansbee increasing Aid to Construction to
$831,000
|
|
January 2006
|
BCPSD requested TEI to review additional alternatives for
treatment
|
|
January 2006
|
Analyzed option of treatment by City of Weirton. This option was not cost effective
|
|
January 2006
|
Analyzed option of treatment by the Village of Mingo Junction.
This option was eliminated due to EPA constraints
|
|
January 2006
|
Email to Follansbee asking if 40,000 GPD could be treated
without WWTP upgrades
|
|
February 2007
|
Letter to Follansbee requesting required upgrades and
treatment costs to serve 191 customers
|
|
February 2006
|
Email to Follansbee asking if 191 customers could be
accepted with no treatment plant upgrades
|
|
September 2006
|
Opened negotiations with City of Wellsburg
|
|
September 2006
|
Letter from Wellsburg offering rate of $5.54 and Aid to
Construction of $550,000
|
|
December 2006
|
Letter from Norfolk Southern Railroad stating force mains
to Follansbee WWTP will need to be encased
|
|
December 2006
|
Email to Follansbee requesting required upgrades to serve
191 customers
|
|
February 2007
|
Meeting between BCPSD and Follansbee to discuss accepting
only 191 customers and required upgrades to accommodate this flow
|
|
March 2007
|
Agreement reached between BCPSD and City of Wellsburg for treatment
by Wellsburg
|
|
March 2007
|
BCPSD voted to amend Infrastructure application
|
|
April 2007
|
Letter from Follansbee stating they would only be willing
to participate if they treated all sewage
|
|
April 2007
|
Amendment to Infrastructure application filed to create an
additional alternative for wastewater treatment and disposal
|
|
April 2007
|
Wellsburg filing of Infrastructure application for system
upgrades
|